Modern Australian
Men's Weekly

.

Snowy 2.0 will not produce nearly as much electricity as claimed. We must hit the pause button

  • Written by Bruce Mountain, Director, Victoria Energy Policy Centre, Victoria University

The federal government’s much-vaunted Snowy Hydro expansion is supposed to smooth out the bumps in electricity supply as Australia transitions to renewables. But not only is the project a bad deal for taxpayers, our analysis suggests it will deliver a fraction of the energy benefits promised.

Fossil-fuel power generators store coal or gas at the point of production. This means electricity can mostly be created on demand when homes and businesses need it. Renewable energy cannot do this. If wind or sun is not abundant, solar panels and wind turbines may not produce enough electricity to meet demand. At other times they might produce more than required.

The Snowy 2.0 project is supposed to provide a solution to this problem - storing renewable energy for when it is needed.

The project’s cost and time estimates have blown out massively. It would now be surprising if Snowy 2.0, including the transmission upgrades it relies on, comes in at less than A$10 billion or is finished before 2027.

But there is another serious problem. Our analysis has revealed that of the extra pumped hydro capacity promised by the project, less than half can be delivered. There is now overwhelming evidence the project should be put on hold.

Snowy 2.0 will not produce nearly as much electricity as claimed. We must hit the pause button The Tumut 3 scheme, with which Snowy 2.0 will share a dam. Snowy Hydro Ltd

The problems we know about: cost and time blowouts

The list of possible alternatives to Snowy 2.0 is long. Aside from other pumped hydro projects, it includes chemical batteries, encouraging demand to follow supply, gas or diesel generators, and re-orienting renewable generators to capture the wind or sun when it is less plentiful.

But despite this plethora of options, the federal government announced the Snowy 2.0 project without a market assessment, cost-benefit analysis or indeed even a feasibility study.

Read more: The government's electricity shortlist rightly features pumped hydro (and wrongly includes coal)

When former Prime Minister Malcolm Turnbull announced the expansion project in March 2017 he said it would cost A$2 billion and be commissioned by 2021. This was revised upwards several times and in April this year, a A$5.1 billion contract for partial construction was awarded. This excludes the costs of transmission and other considerable expenses.

The main contractor says the project will take eight years to build - bringing us to 2027 before the full scheme is completed. We will happily wager that more delays and cost increases will be announced.

Snowy 2.0 will not produce nearly as much electricity as claimed. We must hit the pause button Then prime minister Malcolm Turnbull during a tour of Tumut 3 power station when announcing the expansion in 2017. Lucas Cochairs/AAP

Snowy Hydro has not costed the transmission upgrades upon which the project depends. TransGrid, owner of the grid in New South Wales, has identified options including extensions to Sydney with indicative costs up to A$1.9 billion. Massive extensions south to Melbourne will also be required.

Snowy Hydro contends it should not pay for the new transmission lines because the benefits would flow to the entire grid, not just its venture. In other words Snowy Hydro argues, conveniently, that we should count the benefits but ignore the costs when thinking about their project.

The numbers simply do not add up

The Snowy 2.0 project grandly claims it could generate at its full 2,000 megawatt capacity for 175 hours - or about a week. This capacity can also be expressed as 350 gigawatt hours (GWh).

Energy Minister Angus Taylor has talked up the project’s superiority to smaller-capacity alternatives such as batteries.

But the maximum additional pumped hydro capacity Snowy 2.0 can create, in theory, is less than half this. The reasons are technical, but worth taking the time to understand.

The figure below outlines the main physical features that define Snowy 2.0. It includes four dams: Tantangara, Talbingo, Jounama and Blowering. For simplicity, we have numbered these from 1-4 in the following explanation.

Snowy 2.0 will not produce nearly as much electricity as claimed. We must hit the pause button The Conversation, CC BY-ND When Snowy 2.0 generates electricity, water will be released from Dam 1 at the top of the system. It will flow through a long tunnel to the smaller Dam 2. The flow of water drives turbines which generate energy. When the turbines are reversed, the water is pumped back to the top to continue the cycle. For Snowy 2.0 to produce the 350 GWh of electricity claimed, the top dam must be full and all that water released through the system. But replenishing the top dam after this event would take many months of pumping water from elsewhere in the system, and use up 40% more electricity than was originally generated. So the 350 GWh would never be achieved because it is extremely inefficient and inflexible. In reality, the pumped hydro capacity of Snowy 2.0 is defined by the amount of water that the smaller Dam 2 can hold. If the scheme was a closed system, with no other water flowing in or out, it could produce around 230 gigawatt hours (GWh) of electricity. But the system does not exist in isolation. Part of the existing Snowy Hydro scheme, known as Tumut 3, also uses Dam 2. It creates pumped hydro electricity by cycling water between that dam and the even smaller Dam 3 below it. For Snowy 2.0 to operate at full cyclical capacity, Dam 2 must be empty to receive the water. That would entail emptying Dam 2 into the smaller Dam 3 and from there to Dam 4 at the bottom of the system. This water could not be used again to generate electricity. This “lost” water would have generated 60 GWh worth of electricity in the Tumut 3 scheme. Snowy 2.0 will not produce nearly as much electricity as claimed. We must hit the pause button Khancoban Dam, part of the soon-to-be expanded Snowy Hydro scheme. Snowy Hydro Ltd This means that as a cyclical pumped hydro system, Snowy 2.0 does not add 230 GWh of capacity. When you subtract the 60 GWh from the 230 GWh, Snowy 2.0 adds just 170 GWh of recyclable pumped hydro. This is less than half the claimed storage capacity. And this is the maximum cyclical capacity in theory only. Snowy 2.0 would never produce continuously for the time needed to generate and then pump 230 GWh because it would never be economically viable to run it this way. In practice if Snowy 2.0’s lower dam is operated in future as it is now – almost always close to full – the cycling capacity of Snowy 2.0 may be as low as 40 GWh – around one tenth of the promised number. What does all this mean? These facts put Snowy 2.0 in a completely different light. There are many competing alternatives that can provide storage far more flexibly for a fraction of Snowy 2.0’s price tag. These alternatives would also have far fewer environmental impacts or development risks, in most cases none of the transmission costs and could be built much more quickly. It is always difficult to press the pause button on a major project once it has begun. But the evidence for doing this is overwhelming. In pursuit of the public interest, the federal government should put the project on hold and ask a reputable investment bank to publicly advise, perhaps through the Productivity Commission, what Snowy 2.0 would be worth if built. A credible independent valuation would establish with some confidence how deeply Snowy Hydro will have its hands in the public’s pockets. A panel of independent experts should then be asked to publicly advise whether taxpayer money is needed to meet the demands of a renewables-dominated power system, and if so, the best way it should be spent.

Authors: Bruce Mountain, Director, Victoria Energy Policy Centre, Victoria University

Read more http://theconversation.com/snowy-2-0-will-not-produce-nearly-as-much-electricity-as-claimed-we-must-hit-the-pause-button-125017

Driving Innovation and Reliability with a Professional Engineering Company Melbourne

Engineering is at the core of modern infrastructure, manufacturing, and construction. From the tallest skyscrapers to the most advanced energy syste...

Telematics: Driving Business Efficiency

Telematics, the clever combination of telecommunications and information technology, has evolved from simple vehicle tracking to become an indispens...

5 Signs Your Pool Filter Needs Professional Cleaning

Is your pool water looking cloudy, your pump working overtime, or the jets losing pressure?  These are common warning signs that your pool filter mi...

Social Media: Is It Increasing Rates of Anxiety and Depression?

In today’s connected world, social media has become an integral part of daily life. Platforms like Instagram, TikTok, and Facebook offer opportuni...

Preventive Maintenance Tips for Hydraulic Equipment

Hydraulic equipment plays a crucial role in industries ranging from construction and mining to agriculture and manufacturing. Whether it’s powerin...

Choosing the Right LiDAR System for Your Project

When planning a project that relies on accurate spatial data, selecting the right LiDAR system is one of the most critical decisions you’ll make. ...

The History of Craft Beer: From Monasteries to Modern Breweries

Craft beer has a rich and fascinating history that stretches back centuries. What we enjoy today in trendy taprooms and bustling breweries is the re...

How Natural Pearls Shaped Trade Routes and Global Economies

Throughout history, natural pearls—those rare, untamed treasures formed by nature itself—have exerted a powerful influence on trade networks, po...

How To Choose The Right Insulation For Your Space

Selecting the appropriate insulation for your home or building is a critical decision that affects comfort, energy efficiency, and present and future ...

7 Best Things to Do in Beaufort, Victoria

Beaufort is a charming small town in Victoria’s Goldfields, full of history, natural beauty, and warm, welcoming locals. Whether you’re passing th...

What to Expect During Divorce Mediation & Settlement

Divorce can be a difficult and emotionally draining process, but mediation and settlement often provide a constructive path forward. Instead of goin...

Navigating Disability Services in Perth: Your Questions Answered

Understanding the landscape of disability support can feel overwhelming, especially when you're just starting out. If you’re looking for support a...

How Veneers and Dental Implants Work Together for Full Smile Restoration

Modern dentistry has strong instruments that can produce life-changing outcomes when it comes to repairing a smile that has been impacted by tooth los...

Gen Z’s Are Going off Grid – But Is It Sustainable?

Australia’s cost of living crisis is causing Gen Z to get creative with frugal living options. Earlier this year, young couple Koby and Amelie wan...

The Risks of DIY Air Conditioning Installation and How to Avoid Them

Air conditioning is essential in Australia, especially during the scorching summer months, when homes and workplaces can become unbearable without rel...

How to Find Reliable Air Conditioning Services Near You in Brisbane Northside

Introduction In Brisbane’s hot and humid climate, air conditioning has become more of a necessity than a luxury. Whether it's keeping your home coo...

Enhance Outdoor Living with Lifestyle Awnings

Creating the perfect balance between indoor comfort and outdoor living is something many homeowners aspire to achieve. In recent years, Lifestyle Aw...

Why Buckets with Lids Are Essential for Safe Storage & Transportation

The right bucket can streamline transport and make handling easier day to day. With options suited to food, chemicals and construction materials, th...