I'm not an apologist for the Snowy 2.0 hydro scheme – but let's not obsess over the delays and cost blowouts

  • Written by Andrew Blakers, Professor of Engineering, Australian National University

The first power from the Snowy 2.0 pumped hydro project may not be delivered until 2028, it was revealed yesterday, triggering a fresh round of criticism over the controversial project.

The delay is undoubtedly inconvenient. But, despite speculation, the hold-up won’t noticeably slow the transition to renewable energy. The shift is driven by the compelling price advantage of solar and wind over coal and gas.

And in my view, we shouldn’t get too obsessed about exactly when Snowy 2.0 will be finished, or whether it costs more than first envisaged. In huge projects such as these, delays and cost blowouts are to be expected. And Snowy 2.0 offers us many lessons that will benefit subsequent pumped hydro projects.

I’m not an apologist for Snowy 2.0. I would have preferred it wasn’t built in a national park. But Australia’s renewable energy transformation will require a huge amount of energy storage – and the Snowy extension is an important part of the mix.

man in orange vest touches tunnel wall
Then prime minister Malcolm Turnbull visits Snowy Hydro in 2017. The Snowy 2.0 project is important for Australia’s energy shift. Alex Ellinghausen/AAP

A big deal for powering Australia

Federal government-owned Snowy Hydro on Wednesday said Snowy 2.0 may not begin initial operation until the second half 2028 and may not be fully online until December 2029. It is also likely to suffer further cost blowouts beyond its current price tag of A$5.9 billion.

The project was originally costed at $2 billion and was expected to start operating in 2021.

In a statement, Snowy Hydro attributed the latest delay to COVID-19, global supply chain disruption, technical complications and geological issues.

Snowy 2.0 is the biggest energy storage project under construction in Australia. Pumped hydro storage involves two small reservoirs spaced a few kilometres apart, one built 400-800 metres higher than the other, with tunnels connecting them.

On sunny and windy days, electricity is stored by pumping water up to the higher reservoir. Later, when energy is needed, the water is released downhill through the turbine to produce electricity. The same water goes up and down the hill for the life of the project.

The Albanese government has set a national target of 82% renewable electricity by 2030 – most from solar and wind. These are intermittent energy sources, meaning they sometimes produce more energy than we need, and sometimes less. Energy storage helps smooth bumps in supply.

Solar and wind energy generation in the national electricity market meets about one-third of demand, up from 1% in 2009 and 9% in 2017. So at the moment, we don’t need much energy storage because existing coal, gas and hydroelectric power stations still help balance electricity demand.

But by 2028, solar and wind are expected to generate about 60% of electricity in the market. By then, many more coal plants will have closed, and we’ll need other ways to balance supply and demand. That’s where Snowy 2.0 and other projects come in.

wind turbines on a hill
Energy storage helps smooth electricity supplies from solar and wind. Russell Freeman/AAP

A suite of options needed

So how do we make sure Australia’s electricity supplies remain reliable throughout the renewable energy transition? With a suite of technologies and projects.

The top priority is lots of new transmission infrastructure – mostly high-voltage cables and associated towers, as well as transformers.

This infrastructure is needed to move power generated by new solar and wind projects in rural areas to the cities, and also between states.

Importantly, strong energy transmission between states hugely reduces the need for energy storage by smoothing out local weather. If it’s a wet, windless week in Victoria, electricity can be sent from New South Wales and South Australia. The following week, Victoria might return the favour.

Many other current and future options exist to balance out electricity supplies. They include:

  • off-river pumped hydro
  • grid-scale batteries
  • hot water storage tanks in homes and factories
  • high temperature thermal storage in factories to displace gas furnaces
  • activities to reduce electricity demand at peak times (known as demand management)
  • legacy gas turbines operating only occasionally
  • electric vehicle batteries.

The Snowy 2.0 delays mean other storage methods will take a stronger role in the interim.

Read more: What is the electricity transmission system, and why does it need fixing?

large battery and wind turbines
Grid-scale batteries are part of the future energy mix. Red Havas

Pumped hydro vs the alternatives

Grid-scale batteries are useful for short-term energy storage – seconds, minutes and hours.

Several big battery projects are being deployed in Australia. This includes a project by German energy company RWE, which was just awarded a major NSW government contract. It will generate 50 megawatts of power continuously for eight hours, and so has an energy storage capacity of 400 megawatt-hours.

But pumped hydro excels at overnight and longer energy storage. Globally, pumped hydro constitutes about 95% of electricity storage.

Australia has about 5,500 potential pumped hydro sites. Since we only need ten or 20 pumped hydro systems, we can afford to be very choosy.

Australia has three operating pumped hydro energy storage systems. Two are under construction, including Snowy 2.0, and a dozen others are being planned including big systems in Queensland and Tasmania.

Pumped hydro uses water, whereas batteries use far more expensive electrochemicals. And hydro systems last much longer than big batteries. It’s not a question of choosing between batteries and pumped hydro. We need both.

Snowy 2.0 will have the capacity to generate 2,000 megawatts of continuous power for a whole week, and so will provide about 350,000 megawatt-hours of storage.

This is 40 times more power capacity than the 50 megawatt RWE battery, and about 900 times the energy storage.

The Pioneer-Burdekin pumped hydro system being developed in Queensland will be able to generate 5,000 megawatts of power for 24 hours. This is 100 times more power and 300 times more energy storage than the RWE big battery.

What about the cost?

Upwards of $6 billion is not an insubstantial amount of money. But Snowy 2.0 would have been a bargain if it was completed for $2 billion. And even at, say, $9 billion, the project is still small compared to the $17 billion Australia spends collectively each year on rooftop solar, windfarms, solar farms, electricity storage and powerlines.

The decision to locate Snowy 2.0 in a national park has been intensely criticised. Indeed, my colleagues and I recently identified several attractive alternative sites for 500,000 megawatt-hour pumped hydro projects just a few kilometres west of Snowy 2.0, outside national parks, which you can see in this interactive map. Each would require only a short tunnel and a single new reservoir.

However, at the time the Turnbull government committed to Snowy 2.0, it was the only large-scale storage option on the table. And it’s now fairly far down the construction track.

Read more: Snowy 2.0 threatens to pollute our rivers and wipe out native fish

mountains, lake and mist
The decision to build the Snowy 2.0 project in a national park has been criticised. AAP

Snowy 2.0 is worth doing

Solar and wind could provide virtually all future energy both in Australia and globally.

This would eliminate three-quarters of Australia’s greenhouse emissions. But it requires a doubling of electricity generation, supported by up to one million megawatt-hours of energy storage.

So for the sake of the renewables transition, let’s hope Snowy 2.0’s technical and financial difficulties are resolved.

Read more: Batteries of gravity and water: we found 1,500 new pumped hydro sites next to existing reservoirs

Authors: Andrew Blakers, Professor of Engineering, Australian National University

Read more https://theconversation.com/im-not-an-apologist-for-the-snowy-2-0-hydro-scheme-but-lets-not-obsess-over-the-delays-and-cost-blowouts-204915

Simple Ways to Make a Commercial Property More Appealing to Buyers

Selling or leasing a commercial property isn’t just about listing the square metres, taking a few photos and waiting for the right person to appea...

What Café Owners Should Know Before Upgrading Their Display Setup

A café display fridge does a lot more than keep cakes cold and sandwiches fresh. It quietly shapes the way customers browse, the way staff move beh...

Creating a Backyard That Feels Comfortable All Year Round

A great backyard doesn’t need to be huge, expensive or perfectly styled. Most of the time, the spaces people actually use are the ones that feel e...

How Homeowners Can Make Smarter Energy Decisions Before Upgrading

Energy upgrades used to feel like something you only looked into after a power bill gave you a nasty surprise. These days, though, more homeowners a...

Why Retail CX Breaks During Peak Sales Events and How to Prevent It

Retail customer experience has become one of the most important drivers of revenue growth, especially during high-intensity sales periods. However, ev...

15 South Indian Dishes Everyone Should Try

If your only experience of "Indian food" is butter chicken and garlic naan, South Indian cuisine is going to feel like discovering an entirely new c...

What Every Homeowner Should Know About Roof and Drainage Maintenance

A home's roof and drainage system work together every day to protect the property from water damage. While many homeowners focus on visible areas such...

From Plans to Priced Quote: The Estimating Workflow Most Builders Skip

For a small one-off job, an experienced builder can size up the materials in their head. The problem is that most jobs are not small one-off jobs, and...

Organisational Experts Share Their Tips for Achieving a Clutter-Free Kitchen

They say the kitchen is the heart of a house which means a clutter-free kitchen not only makes your home in general look nicer, it also makes cookin...

10 Creative Ways AI Image Extenders Are Transforming Digital Content Creation in 2026

Introduction Artificial intelligence continues to reshape the digital landscape, and one of the most exciting innovations in 2026 is the rise of AI i...

What to Do When You're Arrested in Victoria

Most people have thought about this in the abstract. A knock at the door, a hand on the shoulder, a car pulled over on the Hume. In the abstract, th...

Common Financial Disputes During Separation

Separation hits on many levels, not just emotionally. When a partnership ends, untangling the financial side — assets, debts, and everything built t...

Why Posting More Content is Killing Your Brand

More content. More often. More platforms.Most brands have been running this playbook for three years. Most brands have nothing to show for it.Not be...

Garden Clean-Up vs. Regular Maintenance: Which Do You Really Need?

Most people ring a gardener and ask for a "tidy up." What they mean by that, and what the garden actually needs, are often two completely different ...

Solar Panel Maintenance Tips for Melbourne Homes

Three years in and the panels are still on the roof. The inverter is still blinking. The electricity bills are still lower than they used to be, rou...

Cost Effective Kitchen Renovations – From the Ground Up

Even in times of uncertainty, it seems renovations continue to be on the to-do list for many Australian property owners. As a result, demand on materi...

Why Bathroom Product Selection Matters More Than Most Homeowners Realise

Most homeowners think wrong when it comes to a bathroom renovation. They think hard about the layout. Spend hours choosing tiles. Agonise over pain...

How An Asbestos Removalist Ensures Safe And Compliant Property Environments in Melbourne

Maintaining a safe environment within residential and commercial properties requires careful management of hazardous materials, which is why engaging ...